Contracts • Excuse of Non-Performance
K#138
Legal Definition
A modification—also known as a "substituted agreement"—is an agreement by the parties to an existing obligation to accept a different agreement in satisfaction of the existing obligation.
Plain English Explanation
Imagine if Bob and Sam entered into an agreement where Bob agreed to pay $100 for Sam to provide 200 tacos. Unfortunately, Sam only has 50 taco-sized tortillas on hand and, due to a global pandemic, it's almost impossible to find them anywhere. In fact, it would cost $200 just to purchase the needed tortillas. Luckily, Sam has plenty of burrito-sized tortillas. However, Sam has no right to substitute a burrito for a taco without Bob agreeing to it. So Sam explains this to Bob and says, "Look, I can't get you 200 tacos, but I'm willing to make you 150 burritos at the same price even though they usually cost twice as much. I'm willing to do this if you rescind our previous agreement." Bob says, "Ok, I agree."
If Bob and Sam were to just agree to discharge their previous agreement and substitute it with a new one, it would be considered a modification. However, by making the first contract's recission conditioned on Sam's performance of the new agreement, it is an accord and satisfaction. That's basically the difference between a "modification" and an "accord and satisfaction."
With an "accord and satisfaction," the "accord" is the new agreement that is proposed, but it doesn't inherently discharge the original agreement. Only when the "satisfaction" is performed does it discharge the prior obligation. In contrast, a "modification" swaps out one agreement with a different agreement.
If Bob and Sam were to just agree to discharge their previous agreement and substitute it with a new one, it would be considered a modification. However, by making the first contract's recission conditioned on Sam's performance of the new agreement, it is an accord and satisfaction. That's basically the difference between a "modification" and an "accord and satisfaction."
With an "accord and satisfaction," the "accord" is the new agreement that is proposed, but it doesn't inherently discharge the original agreement. Only when the "satisfaction" is performed does it discharge the prior obligation. In contrast, a "modification" swaps out one agreement with a different agreement.
Visual Aids
Related Concepts
How is performance affected when the subject matter of the contract is damaged or destroyed?
Under common law, is late performance a material breach?
Under common law, when is counter-performance excused?
Under common law, when may a breaching party recover in a divisible contract?
What is excuse due to anticipatory repudiation?
What is excuse due to improper performance?
What is frustration of purpose?
What is impracticability?
What is the doctrine of impossibility?
What level of compliance is required to satisfy an express condition?
What options does the non-breaching party have in response to an anticipatory repudiation?